FAR 52.203-13 is prescribed for a contract expected to exceed $7.5 million with a performance period of 120 days or more. A small business or commercial-product contractor is excused from the clause’s formal business-ethics awareness program and internal-control-system requirement. It is not excused from the clause’s written code requirement or its duty to timely disclose credible evidence of specified fraud, conflict, bribery, gratuity, or civil False Claims Act violations to the agency Inspector General, with a copy to the contracting officer.

The threshold comes first

FAR 3.1004 directs agencies to insert the clause when the expected value exceeds $7.5 million and performance will last 120 days or more. Check the actual solicitation and any modifications. A clause’s presence controls the contract duty.

What does a small business still do?

Within 30 days after award, the clause calls for a written code of business ethics and conduct, made available to employees working on the contract. The small-business and commercial-product exception applies to paragraph (c), which covers the awareness program and internal controls. It does not erase paragraph (b). The exception can’t remove the written-code duty.

See how to review a solicitation, DFARS 252.204-7012, and CMMC for subcontractors for adjacent contract review work.

What does the disclosure duty cover?

Paragraph (b) uses “credible evidence.” It covers specified federal criminal-law violations involving fraud, conflict of interest, bribery, or gratuity, and violations of the civil False Claims Act, connected with the award, performance, or closeout of a Government contract or subcontract. The recipient is the agency Office of Inspector General, with a copy to the contracting officer.

This is a decision point for counsel and the facts, not a demand to report every operational error. Preserve the record, identify the relevant contract or subcontract, and obtain legal advice promptly when credible evidence appears. Deep Fathom recommends keeping the decision, supporting records, reviewer, and response dates together for a later review.

An exception does not create immunity

FAR 3.1003 separately identifies knowing failure to timely disclose credible evidence as a cause for suspension or debarment, until three years after final payment. Whether it applies to a particular event depends on the facts and governing law. This page does not decide that question for a contractor. A small-business label can’t end the review.

For the broader contract context, see the CMMC overview.

References

References · 3 official sources
SourceWhat it supportsType
FAR 52.203-13Code, disclosure, and paragraph (c) exceptionRegulation
FAR 3.1004Clause thresholdRegulation
FAR 3.1003Suspension/debarment groundRegulation